FPL wants more nuclear units; customers say prove they make sense


Just weeks after this summer’s announcement that two unfinished nuclear reactors in South Carolina are being abandoned, Florida regulators are poised to once again consider Florida Power & Light’s pursuit of two new reactors.

However, hundreds of FPL customers say they want the utility to prove the reactors would be worth the costs. In an email campaign organized by the Southern Alliance for Clean Energy, they’re asking the commission to reject FPL’s “heavy-handed and unprecedented request” for a deferral of a required annual feasibility study for the two proposed Turkey Point reactors.

NUCLEAR PANEL SAYS PLAN TO INJECT WASTEWATER INTO GROUND IS OKAY

The feasibility study is meant to answer the question of whether a project makes economic sense for customers.

FPL SEEKS TO DEFER CHARGING CUSTOMERS FOR NEW NUKES

The hearing before the Florida Public Service Commission begins Tuesday at 1:30 p.m. in Tallahassee, and can be viewed at Floridapsc.com

FPL, headquartered in Juno Beach, has sought the operating license for the new units from the U.S. Nuclear Regulatory Commission since 2009. The company says it wants to continue that process for the proposed 2,200-megawatt Turkey Point 6 and 7 reactors, which could cost as much as $21.8 billion. They might never be built, or no sooner than 2031, could join two existing reactors at the plant overlooking Biscayne Bay south of Miami.

NUCLEAR REGULATORS INSPECTED PLANT IN MARCH AFTER ELECTRICAL FAULT

The reactors have already cost FPL customers $282 million in pre-licensing costs. FPL has applied for a license for two AP-1000 reactors, designed by Westinghouse. Westinghouse, which filed for bankruptcy in March along with its parent company, Toshiba, was hired to construct two AP-1000 reactors at the failed V.C. Summer nuclear project in South Carolina. Two utilities there said in late July they were ending the project after spending $9 billion on the reactors less than 40 percent completed.

FPL customers have sent hundreds of identical emails to the PSC asking it to deny FPL a waiver on providing a detailed analysis of the long-term feasibility of completing the power plant. The commission’s own rules require the study to be filed each year.

“I have already paid too much for too long toward this phantom project, as have all other FPL customers,” Robert OBrien of Delray Beach wrote.

David Garrett of Wellington wrote: “It is not fair for the company to continue to heap the financial risk onto customers like me to pursue new reactors at Turkey Point, a project for which there is no builder. I understand the builder, Westinghouse, filed for bankruptcy and is out of the nuclear construction business. And apparently FPL will not commit to actually build the reactors, nor will it commit to a price tag. Further, the company can’t even show that the reactors are in the best economic interests of their customers.”

FPL spokesman Peter Robbins said that while, of course, FPL officials are aware of what happened in South Carolina, “we are not going to cancel this project.”

Robbins said it would not be appropriate or a good use of money to conduct another feasibility study until after the license is obtained. FPL plans to effectively “pause” the project before moving into the pre-construction phase. Feasibility studies cost roughly $750,000, he said.

In 2016, the PSC granted FPL’s request for a deferral of a new feasibility report, and at that time, FPL said it would file the analysis this year. Now the company wants to delay the report for at least four years. It’s asking the commission find that it is reasonable for the company to pursue the license and recover costs later from its customers.

The Office of Public Counsel, the Florida Industrial Power Users Group, the Florida Retail Federation, the City of Miami and the Southern Alliance for Clean Energy all oppose FPL’s requests.

FPL argues in pre-filed testimony that it is not required to provide a long-term feasibility study because it isn’t seeking to recover costs from customers for several years. OPC calls that argument “meritless,” and says that according to FPL’s testimony, over a 10-year period, customers could become liable for more than $100 million in additional licensing-related costs, including carrying costs.

Construction of two AP-1000 reactors at the existing Vogtle nuclear power plant in Georgia is still underway, but has experienced delays and cost overruns. Southern Nuclear, parent company of Georgia Power, has replaced Westinghouse as the primary contractor in the expansion.

The South Carolina and Georgia projects’ problems, along with other factors, call into question whether FPL’s continued pursuit of the license and related costs is realistic and practical, Public Counsel J.R. Kelly said in a filing.

Stephen Smith, executive director, Southern Alliance for Clean Energy, said the group asked FPL customers among its contacts to send emails to the PSC.

“The PSC needs to understand they are on thin ice here. They set the rules. They cannot blame this on anybody else. If they grant FPL an additional waiver on not even to having to do a feasibility study for a second year in a row … they are violating their own rules,” Smith said.

“It will be extraordinarily difficult for them, with a straight face, to write an order that gives FPL a pass on their own rules. FPL ratepayers need to have their eyes wide open,” Smith said.

While FPL is not asking for money right now, they will come back and charge customers later.

“It’s like saying you will continue to rack up charges on a credit card. At some point you will have to pay. We don’t think these reactors will ever get built,” Smith said.

Proposed Turkey Point nuclear reactors

If built, units 6 and 7 would join two existing reactor at FPL’s plant 25 miles south of Miami.

Projected cost is $14.96 billion to $21.8 billion

The earliest they would start operating is 2031.

FPL plans to inject millions of gallons of wastewater from units’ cooling system into 13 deep wells in the Boulder Zone underlying the site overlooking Biscayne Bay.

Source: Florida Power & Light



Reader Comments ...


Next Up in

HOA board may have power to regulate exterior of your home

Question: I live in a small development governed by an HOA. Our declaration of covenants states that “no patio-villa owner shall in any way deface or change the color of the exterior of his patio-villa. Exterior walls, roof and the fencing around the courtyard are to be maintained by each patio-villa owner in quality condition at all times.&rdquo...
FPL asks PSC to agree new Dania Beach plant is needed
FPL asks PSC to agree new Dania Beach plant is needed

Florida Power & Light wants to build another natural gas-fired plant, but first the Florida Public Service Commission has to agree that the proposed Dania Beach Clean Energy Center Unit 7 is needed. On Friday, Juno Beach-based FPL filed a formal petition asking the PSC to affirmatively determine that a modernized $888 million 1,163 megawatt facility...
After Irma: Storm slows hiring, home sales, muddies economy
After Irma: Storm slows hiring, home sales, muddies economy

Hurricane Irma disrupted Florida’s economy in September, slowing job growth and scotching home sales. Even so, the storm seemed to deliver only a glancing blow to the state’s labor and housing markets. Palm Beach County’s jobless rate fell to 3.6 percent and Florida unemployment dipped to 3.8 percent, both decade-long lows. NEW: Westlake...
Electric vehicles: What has to happen to increase popularity?
Electric vehicles: What has to happen to increase popularity?

Electric vehicles ride quietly, will run without gasoline and can be “filled-up” at a charging station at home. So why do they make up well below 1 percent of the 250 million vehicles on the road in the U.S.? The higher up-front cost of an EV along with “range anxiety” about how far a vehicle can travel on a charge are among...
Westlake builder stresses affordable housing, down-payment help
Westlake builder stresses affordable housing, down-payment help

The massive new Westlake development in western Palm Beach County will entice middle-class home buyers with down-payment grants of 3 percent of the purchase price, builder Minto Communities said this week. The funding source for the program already is raising some eyebrows: Minto Communities said it will impose a $1,500 fee on every sale and resale...
More Stories